Rooftop chiller replacement, Brisbane CBD

Two 1,180 kg chillers swapped on a 14-storey plant deck inside a single Sunday window, with no street closure.

01

The constraint

The plant deck sat 14 storeys up behind a parapet, set back 9 m from the building line.

The only crane position was a two-lane arterial requiring a full weekend closure and traffic management.

Building management could not surrender tenant access on a weekday, and the chillers were already failing.

02

The lift

Load weight
1,180 kg
Aircraft
Black Hawk UH-60
Line length
45 m
Crew
6
Exclusion zone
60 m
Lift cycles
4

01Flew from Archerfield with a 45 m long line and remote hook, staging the replacement units on a closed carpark deck two blocks north.

02Old units were cut free, rigged and flown out first so the deck was clear before the new plant arrived.

03Riggers on the roof worked inside a marked 60 m exclusion zone under a dedicated ground controller on a discrete frequency.

04Four cycles total: two out, two in, with the deck signed off before the CBD reopened on Monday.

03

The numbers

Time on site
1.5 hrs
Flight time
0.8 hrs
Crane alternative
3 days · $41,500 – $55,500
Road closures
0
04

On site

Rooftop chiller replacement, Brisbane CBD — helicopter lift at Turbot Street, Brisbane CBD, Queensland (frame 1 of 3)
Rooftop chiller replacement, Brisbane CBD — helicopter lift at Turbot Street, Brisbane CBD, Queensland (frame 2 of 3)
Rooftop chiller replacement, Brisbane CBD — helicopter lift at Turbot Street, Brisbane CBD, Queensland (frame 3 of 3)
05

Flight record

Long line operations, Black Hawk UH-60, Turbot Street, Brisbane CBD.

06

Client record

We had quotes for a weekend road closure that cost more than the plant. The aircraft was on site for ninety minutes and the street never shut.

Daniel Reeve · Facilities Manager, Turbot Street Asset Services