Project numberPA-2552LocationCambooya, Darling DownsDate2024-09-22
← Project register

Transmission pole change-out, Darling Downs

Eleven concrete poles replaced across cropped paddocks without a single machine track through standing sorghum.

01

The constraint

The easement crossed 4 km of irrigated cropping with landholder agreements limiting ground disturbance.

Wet-season subsoil could not carry a 60 t crane or a pole trailer.

Outage windows were capped at eight hours per feeder.

02

The lift

Load weight
1,420 kg
Aircraft
Black Hawk UH-60
Line length
50 m
Crew
8
Exclusion zone
70 m
Lift cycles
22

01Poles were staged in threes on a hardstand beside the highway and flown in sequence.

02Old poles were flown out to the same laydown for disposal, keeping the easement clear.

03Linesmen worked from elevated platforms only where road access already existed; all other structures were serviced from the air.

04Twenty-two cycles across one day inside two outage windows.

03

The numbers

Time on site
6.4 hrs
Flight time
4.1 hrs
Crane alternative
9 days · $118,000 + crop compensation
Road closures
0
04

On site

Transmission pole change-out, Darling Downs — helicopter lift at Cambooya, Darling Downs, Queensland (frame 1 of 3)
Transmission pole change-out, Darling Downs — helicopter lift at Cambooya, Darling Downs, Queensland (frame 2 of 3)
Transmission pole change-out, Darling Downs — helicopter lift at Cambooya, Darling Downs, Queensland (frame 3 of 3)
05

Flight record

Long line operations, Black Hawk UH-60, Cambooya, Darling Downs.

06

Client record

Eleven structures in a day with no crop damage claims. The paddock looked the same at knock-off as it did at dawn.

Ian Crowther · Network Delivery Manager, Downs Energy Services