Water tank placement, Moreton Island
Six poly tanks and a pump skid placed at an island resort with no barge window and no vehicle access to the ridge.
PA-2588 · Eastern ridge, Moreton Island · 2025-01-28

The constraint
Why this lift needed a helicopter
Tanks had to reach a ridge 1.4 km beyond the last trafficable sand track.
Barge scheduling was tide dependent and the resort could not close the beach access for a week.
Cutting a temporary track through vegetated dune required approvals nobody was going to obtain in the timeframe.
The lift
How it was flown
- Load weight
- 740 kg
- Aircraft
- AS350
- Line length
- 30 m
- Crew
- 5
- Exclusion zone
- 45 m
- Lift cycles
- 7
- Loads were staged on the mainland at a cleared laydown near the barge ramp and flown across in seven cycles.
- Each tank flew empty on a 30 m line with a spreader to prevent shell distortion.
- Ground crew on the ridge landed each load onto pre-levelled pads and released remotely.
- The pump skid went last so plumbing could begin the same afternoon.
The numbers
Time, cost and disruption
- Helicopter time on site
- 2.6 hrs
- Flight time
- 1.9 hrs
- Crane alternative
- Not achievable · barge + dozer track $86,000+
- Road closures
- 0
On site
Photos
Also filed
More projects

PA-2614 · 2025-03-16
Rooftop chiller replacement, Brisbane CBD
Two 580 kg chiller modules swapped on a 14-storey plant deck inside a single Sunday window, with no street closure.
580 kg · 20 min on site

PA-2571 · 2024-11-09
Spa placement over a hinterland home
A 620 kg acrylic spa flown over a two-storey home into a rear deck with a 3.2 m gate and no side access.
620 kg · 0.6 hrs on site

PA-2552 · 2024-09-22
Transmission pole change-out, Darling Downs
Eleven concrete poles replaced across cropped paddocks without a single machine track through standing sorghum.
620 kg · 6.4 hrs on site