Project numberPA-2399LocationMount Nebo, west of BrisbaneDate2022-06-21
← Project register

Concrete placement to a ridge-top slab

Sixty-two skip cycles of concrete flown to a ridge-top slab a pump could not reach.

01

The constraint

The last 1.9 km of access was a single-lane track with switchbacks a truck-mounted pump could not negotiate.

The pour had to be continuous to avoid a cold joint in a structural slab.

Trucks could only reach a batching turnaround at the base of the ridge.

02

The lift

Load weight
1,100 kg
Aircraft
Airbus H125
Line length
30 m
Crew
6
Exclusion zone
45 m
Lift cycles
62

01A dedicated skip station was set at the turnaround with two agitators rotating.

02Skips were flown on a 30 m line on a fixed 4 minute cycle to hold the pour rate.

03Placement crews worked the slab continuously; the pour closed without a joint.

03

The numbers

Time on site
4.4 hrs
Flight time
3.2 hrs
Crane alternative
Pump not achievable · road upgrade $240,000
Road closures
0
04

On site

Concrete placement to a ridge-top slab — helicopter lift at Mount Nebo, west of Brisbane, Queensland (frame 1 of 3)
Concrete placement to a ridge-top slab — helicopter lift at Mount Nebo, west of Brisbane, Queensland (frame 2 of 3)
Concrete placement to a ridge-top slab — helicopter lift at Mount Nebo, west of Brisbane, Queensland (frame 3 of 3)
05

Client record

Continuous pour on a ridge with no pump access. On paper it should not have happened.

Sam Iremonger · Site Foreman, Nebo Ridge Builders