Tracker frames across a solar farm, Capricornia
Pre-assembled tracker frames distributed across a 320 ha solar farm without a single haul road extension.
PA-2461 · Gracemere, Capricornia · 2023-08-30

The constraint
Why this lift needed a helicopter
Recent rain left rows unable to carry telehandler traffic without rutting the array.
Frames were built at a central bay, 2.4 km from the far rows.
The EPC had a hard energisation date with liquidated damages attached.
The lift
How it was flown
- Load weight
- 760 kg
- Aircraft
- AS350
- Line length
- 35 m
- Crew
- 7
- Exclusion zone
- 50 m
- Lift cycles
- 64
- A repeating racetrack circuit was flown from the assembly bay to each row block.
- Sixty-four cycles were flown across one day with two fuel stops on the site pad.
- Ground crews rotated in pairs to keep hook-up and release times under 40 seconds.
The numbers
Time, cost and disruption
- Helicopter time on site
- 7.2 hrs
- Flight time
- 5.4 hrs
- Crane alternative
- 14 days telehandler cycle · $96,000
- Road closures
- 0
Also filed
More projects

PA-2614 · 2025-03-16
Rooftop chiller replacement, Brisbane CBD
Two 580 kg chiller modules swapped on a 14-storey plant deck inside a single Sunday window, with no street closure.
580 kg · 20 min on site

PA-2588 · 2025-01-28
Water tank placement, Moreton Island
Six poly tanks and a pump skid placed at an island resort with no barge window and no vehicle access to the ridge.
740 kg · 2.6 hrs on site

PA-2571 · 2024-11-09
Spa placement over a hinterland home
A 620 kg acrylic spa flown over a two-storey home into a rear deck with a 3.2 m gate and no side access.
620 kg · 0.6 hrs on site
Ready to book a lift?
Get an indicative price in about a minute, then a written quote.