Skip to content
HELICOPTER LIFTINGpowered by Parker Aero
Project numberPA-2519LocationMaroochydore, Sunshine CoastDate2024-05-19
← Project register

Steel trusses over a live retail centre

Nine roof trusses set over a trading shopping centre between closing time and the morning delivery run.

01

The constraint

The only crane pad was 240 bays of trading carpark, closed for four days.

Trusses had to travel over an occupied tenancy roof with no ground path beneath.

Centre management allowed a single overnight window with the car park empty by 21:00.

02

The lift

Load weight
2,240 kg
Aircraft
Black Hawk UH-60
Line length
50 m
Crew
7
Exclusion zone
70 m
Lift cycles
9

01Trusses were pre-assembled and staged on a vacant lot 900 m from the site.

02Each pick was flown to a fixed approach line agreed with the centre, clear of the tenancy footprint.

03Steel crews bolted off in pairs so the aircraft never held a load in hover longer than 90 seconds.

04Site handed back before the 05:00 delivery run.

03

The numbers

Time on site
2.1 hrs
Flight time
1.3 hrs
Crane alternative
4 days · $62,000 + carpark closure
Road closures
0
04

On site

Steel trusses over a live retail centre — helicopter lift at Maroochydore, Sunshine Coast, Queensland (frame 1 of 3)
Steel trusses over a live retail centre — helicopter lift at Maroochydore, Sunshine Coast, Queensland (frame 2 of 3)
Steel trusses over a live retail centre — helicopter lift at Maroochydore, Sunshine Coast, Queensland (frame 3 of 3)
05

Client record

Four days of closed car park versus two hours after trading. It was not a close decision.

Rob Anderson · Construction Manager, Coastline Projects