Two 2,600 kg beams set across a protected creek where no crane pad could be built on either bank.

01

The constraint

Both banks were vegetated riparian zone with no permissible crane platform.

A temporary causeway needed environmental approval and would have been removed weeks later.

Beam tolerance at the abutments was 15 mm.

02

The lift

Load weight
2,600 kg
Aircraft
Black Hawk UH-60
Line length
50 m
Crew
7
Exclusion zone
70 m
Lift cycles
2

01Beams were staged on a sealed carpark 700 m downstream and rigged with a two-point spreader.

02Survey crews set targets on both abutments so the pilot could fly to a marked line.

03Each beam was walked into bearing by tag line with fitters on both abutments.

03

The numbers

Time on site
1.8 hrs
Flight time
0.9 hrs
Crane alternative
Temporary causeway $148,000 + permits
Road closures
0
04

On site

Pedestrian bridge beams over a creek, Wide Bay — helicopter lift at Tinana Creek, Wide Bay, Queensland (frame 1 of 3)
Pedestrian bridge beams over a creek, Wide Bay — helicopter lift at Tinana Creek, Wide Bay, Queensland (frame 2 of 3)
Pedestrian bridge beams over a creek, Wide Bay — helicopter lift at Tinana Creek, Wide Bay, Queensland (frame 3 of 3)
05

Client record

We saved a causeway, the approvals that came with it, and six weeks of programme.

Dean Mallory · Civil Delivery, Wide Bay Regional Works